Trump ramps up border-wall construction ahead of 2020 vote
The president’s barrier is one of the largest federal infrastructure projects in the nation’s history. Here’s what his administration has built so far and where it plans to build next.
By Nick Miroff and Adrian Blanco Feb. 6, 2020The southern U.S. border has about 650 miles of barriers that take a variety of forms. In more-urban areas, tall “pedestrian” fences are in place to stop people from crossing. In remote areas, the government uses “vehicle barriers” made from old railroad tracks. In mountainous areas and long stretches that follow the Rio Grande, there is no man-made structure.
Fence type:
Pedestrian
Vehicle
No barrier
CALIF.
ARIZ.
N.M.
TEXAS
Tucson
El Centro
El Paso
San Diego
Yuma
Pacific
Ocean
Gulf of
Mexico
Laredo
McAllen
MEXICO
250 MILES
The Washington Post has obtained detailed U.S. government data about Trump’s border-wall project, its construction progress and contracts for each segment of the structure. The data shows the Trump administration is far from delivering on the president’s promise to finish more than 500 miles of new barriers by early next year. Though Trump had insisted Mexico would pay for the project, it has been funded entirely by the U.S. government, at costs that reach nearly $30 million per mile in southern Texas.
[Smugglers are sawing through new sections of Trump’s border wall]
The Trump administration is installing a structure far more formidable than anything previously in place along the border. The new structure has steel bollards, anchored in concrete, that reach 18 to 30 feet in height and will have lighting, cameras, sensors and improved roads to allow U.S. agents to respond quickly along an expanded “enforcement zone.”
Government contractors erect a 30-foot-high section of new Pentagon-funded border wall along the Colorado River in September in Yuma, Ariz. (Matt York/AP)
The San Diego sector of the border wall in April 2018. (Carolyn Van Houten/The Washington Post)
Vehicle barriers across a riverbed along the border in early January near Hereford, Ariz. (Carolyn Van Houten/The Washington Post)
Nearly all of the new fencing the Trump administration has built so far is considered “replacement” fencing, swapping out smaller, older vehicle barriers for a more elaborate — and costly — “border wall system.”
The administration has been slower to build new barriers where none currently exist, primarily because those spans require the acquisition of private land. Even with the slated construction goals, most of the southern border will not have a man-made barrier.
PRE-CONSTRUCTION STATUS OF THE SOUTHERN BORDER
Existing barrier
No barrier
654 miles
1,300 miles
Vehicle
barrier
to be converted
Barrier to
be replaced
Barrier
to remain
Non-priority area
Mostly mountains
Priority area
for new construction
864 miles
221 miles
133 miles
300 miles
436 miles
U.S.-Mexico border, 1,954 miles
Trump has promised to build at least 500 miles of new fencing by early next year, and his administration has completed about 110 miles so far. To meet the president’s targets, crews will need to add about 30 linear miles of barrier per month throughout 2020, more than double the current pace of construction.
Administration goal by the end of 2020
450 miles of new or converted barrier
Overall goal (targeted for Aug. 2021)
509 miles of new or converted barrier
Complete, 110 miles
Under construction, 192 miles
U.S.-Mexico border, 1,954 miles
Data as of Jan. 23
Border-wall status reports obtained by The Post detail how much new construction the administration expects each month to finish 509 miles of new barrier by August 2021.
With the pace of construction lagging behind Trump’s targets, Department of Homeland Security officials have tried to lower expectations, saying they will have 450 miles completed or “under construction” by the end of the year.
EXPECTED VS. ACTUAL CONSTRUCTION PROGRESS
Administration goal:
509 miles of barrier
500
miles
The construction of 450 miles
is expected by the end of 2020
400
300
200
138 miles expected
110 miles completed
as of Jan. 23
100
0
2019
2020
2021
Aug. 2021
Data as of Jan. 23
The Trump administration faces legal and physical challenges to hit its construction targets in Texas, where the Rio Grande forms a natural barrier along hundreds of miles of border.
Unlike in western states, where much of the land already is under government control, there are hundreds of riverfront farms, ranches and other properties in private hands in Texas. Some lack clear ownership records; others are held by multiple heirs. The government plans to make aggressive use of its eminent-domain powers to acquire them, but the process is slow and requires potentially lengthy legal actions.
In many cases, people are unwilling to hand their land over to the government or allow its use for the construction of border barriers, in part because it could split plots and restrict land use, block river access, affect scenic views or reduce land values. Some have vowed to fight.
CONSTRUCTION ON PUBLIC VS. PRIVATE LAND
24% built
7% built
302 miles planned for federal land
208 miles planned for private land
U.S.-Mexico border, 1,954 miles
Data as of Nov. 14
Budget and spending
The White House is planning to divert an additional $7.2 billion from this year’s military budget, bringing the total amount of money available for the project to $18.4 billion, enough to complete nearly 900 miles of new barriers by 2022. Of that, just $5.1 billion has been authorized by lawmakers. The rest is coming from Defense Department funding, primarily through the Pentagon’s counternarcotics accounts and military construction budgets.
Legal challenges to Trump’s authority to spend money that Congress originally authorized for other purposes have at times temporarily blocked this White House tactic, but courts have sided with the administration.
SOURCES OF FUNDING
Each represents $1 millionDepartment of Homeland SecurityRoutine appropiation$5.1 billionDefense DepartmentNational emergency funding$3.6 billion$3.7 billion planned additional fundingDefense DepartmentRoutine appropiation$2.5 billion$3.5 billion planned additional fundingData as of Jan. 23.The private contractors who are receiving this money to build the structure comprise a range of large conglomerates and smaller companies. Most have tried to maintain a low profile, but the CEO of one firm, North Dakota-based Fisher Industries, has pursued an aggressive campaign to promote his company through lobbying efforts and appearances on Fox News.
Trump personally urged military officials to hire Fisher, and the company recently won a $400 million contract. Several lawmakers raised concerns about the bidding process, and the contract is now under review by the Pentagon’s inspector general.
FUND ALLOCATIONS TO PRIVATE CONTRACTORS
Each represents $1 millionSWVC (Kiewit)$1.77 billionSLSCO$1.52 billionBFBC$700 millionSouthern Border Constructors$516 millionFisher Sand and Gravel$400 millionBarnard Construction$322 millionCaddell Construction$297 millionSWF Constructors$25 millionWest Point Contractors$25 millionData as of Nov. 14.Explore the contracts
Explore the billions of dollars in contracts that the federal government has issued for wall construction as of Nov. 14, including completed wall sections, those under construction and those that are considered “pre-construction.”
Fence
No barrier
CALIF.
ARIZ.
N.M.
TEXAS
El Paso
El Centro
Tucson
San Diego
Yuma
Pacific
Ocean
Gulf of
Mexico
Laredo
McAllen
MEXICO
Construction area
250 MILES
Sort by:
Filter by:
COMPLETEEl Centro, Calif.Due by Oct. 13, 2018Construction type: ReplacementLand ownership: FederalContractor: SWF Constructors
Total miles: 2Miles built: 2Progress: 100%$25 million has been allocated to build this section of the wall at a cost of $12.5 million per mile.COMPLETESanta Teresa, N.M.Due by March 18, 2019Construction type: ReplacementLand ownership: FederalContractor: Barnard Construction
Total miles: 20Miles built: 20Progress: 100%$79 million has been allocated to build this section of the wall at a cost of $4.0 million per mile.COMPLETESan Diego, Calif.Due by Sep. 25, 2019Construction type: ReplacementLand ownership: FederalContractor: SLSCO
Total miles: 14Miles built: 14Progress: 100%$153 million has been allocated to build this section of the wall at a cost of $10.9 million per mile.COMPLETEEl Paso, Tex.Due by Nov. 30, 2019Construction type: ReplacementLand ownership: FederalContractor: West Point Contractors
Total miles: 4Miles built: 4Progress: 100%$25 million has been allocated to build this section of the wall at a cost of $6.3 million per mile.UNDER CONSTRUCTIONRio Grande Valley, Tex.Due by Feb. 6, 2020Construction type: Levee wallLand ownership: PrivateContractor: SLSCO
Total miles: 8Miles built: 0Progress: 0.08%$194 million has been allocated to build this section of the wall at a cost of $24.3 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by May 18, 2020Construction type: NewLand ownership: PrivateContractor: Kiewit Infrastructure West
Total miles: 3Miles built: 0Progress: 0%$50 million has been allocated to build this section of the wall at a cost of $16.7 million per mile.UNDER CONSTRUCTIONSan Diego Secondary, Calif.Due by June 3, 2020Construction type: Secondary fenceLand ownership: PrivateContractor: SLSCO
Total miles: 14Miles built: 10.7Progress: 76.33%$132 million has been allocated to build this section of the wall at a cost of $9.4 million per mile.UNDER CONSTRUCTIONYuma, Ariz.Due by June 7, 2020Construction type: ReplacementLand ownership: FederalContractor: Barnard Construction
Total miles: 22Miles built: 25.3Progress: 97.47%$243 million has been allocated to build this section of the wall at a cost of $11.0 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by Aug. 12, 2020Construction type: NewLand ownership: PrivateContractor: Southwest Valley Constructors (Kiewit)
Total miles: 4Miles built: 0Progress: 0%$84 million has been allocated to build this section of the wall at a cost of $21.0 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by Oct. 15, 2020Construction type: Levee wallLand ownership: PrivateContractor: SLSCO
Total miles: 5Miles built: 0Progress: 0%$165 million has been allocated to build this section of the wall at a cost of $33.0 million per mile.UNDER CONSTRUCTIONEl Centro, Calif.Due by Oct. 15, 2020Construction type: ReplacementLand ownership: PrivateContractor: SLSCO
Total miles: 11Miles built: 4.5Progress: 29.96%$140 million has been allocated to build this section of the wall at a cost of $12.7 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by Nov. 7, 2020Construction type: Non-levee wallLand ownership: PrivateContractor: To be determined
Total miles: 14Miles built: 0Progress: 0%$178 million has been allocated to build this section of the wall at a cost of $12.7 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by Nov. 17, 2020Construction type: NewLand ownership: PrivateContractor: Southwest Valley Constructors (Kiewit)
Total miles: 11Miles built: 0Progress: 0%$345 million has been allocated to build this section of the wall at a cost of $31.4 million per mile.UNDER CONSTRUCTIONEl Paso, Tex.Due by Jan 5, 2021Construction type: ReplacementLand ownership: DHSContractor: SLSCO
Total miles: 46Miles built: 2.5Progress: 5.4%$739 million has been allocated to build this section of the wall at a cost of $16.1 million per mile.UNDER CONSTRUCTIONEl Centro, Calif.Due by Nov. 1, 2021Construction type: ReplacementLand ownership: DHSContractor: BFBC
Total miles: 15Miles built: 2.9Progress: 19.1%$319 million has been allocated to build this section of the wall at a cost of $21.3 million per mile.UNDER CONSTRUCTIONYuma, Ariz.Due by Nov. 11, 2021Construction type: ReplacementLand ownership: DHSContractor: BFBC
Total miles: 10Miles built: 0.8Progress: 16.7%$121 million has been allocated to build this section of the wall at a cost of $12.1 million per mile.UNDER CONSTRUCTIONTucson, Ariz.Due by Feb. 2, 2021Construction type: ReplacementLand ownership: DHSContractor: Southwest Valley Constructors (Kiewit)
Total miles: 38Miles built: 0.7Progress: 1.9%$789 million has been allocated to build this section of the wall at a cost of $20.8 million per mile.UNDER CONSTRUCTIONTucson, Ariz.Due by Feb. 2, 2021Construction type: ReplacementLand ownership: DHSContractor: Southwest Valley Constructors (Kiewit)
Total miles: 5Miles built: 0.8Progress: 16.9%$102 million has been allocated to build this section of the wall at a cost of $20.4 million per mile.UNDER CONSTRUCTIONTucson, Ariz.Due by April 2, 2021Construction type: ReplacementLand ownership: FederalContractor: Southwest Valley Constructors (Kiewit)
Total miles: 20Miles built: 0.2Progress: 1.2%$408 million has been allocated to build this section of the wall at a cost of $20.4 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by March 10, 2021Construction type: NewLand ownership: PrivateContractor: Southern Border Constructors
Total miles: 21Miles built: 0Progress: 0%$258 million has been allocated to build this section of the wall at a cost of $12.3 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by March 10, 2021Construction type: NewLand ownership: PrivateContractor: Southern Border Constructors
Total miles: 22Miles built: 0Progress: 0%$258 million has been allocated to build this section of the wall at a cost of $11.7 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by March 10, 2021Construction type: NewLand ownership: PrivateContractor: Caddell Construction
Total miles: 22Miles built: 0Progress: 0%$297 million has been allocated to build this section of the wall at a cost of $13.5 million per mile.PRE-CONSTRUCTIONRio Grande Valley, Tex.Due by March 10, 2021Construction type: NewLand ownership: PrivateContractor: To be determined
Total miles: 2Miles built: 0Progress: 0%$40 million has been allocated to build this section of the wall at a cost of $20.0 million per mile.PRE-CONSTRUCTIONYuma, Ariz.Due by No date yetConstruction type: New secondaryLand ownership: Defense Dept.Contractor: BFBC
Total miles: 31Miles built: 0Progress: 0%$260 million has been allocated to build this section of the wall at a cost of $8.4 million per mile.PRE-CONSTRUCTIONYuma, Ariz.Due by No date yetConstruction type: ReplacementLand ownership: FederalContractor: To be determined
Total miles: 27Miles built: 0Progress: 0%$636 million has been allocated to build this section of the wall at a cost of $23.6 million per mile.PRE-CONSTRUCTIONEl Paso, Tex.Due by No date yetConstruction type: ReplacementLand ownership: DHSContractor: To be determined
Total miles: 30Miles built: 0Progress: 0%$492 million has been allocated to build this section of the wall at a cost of $16.4 million per mile.PRE-CONSTRUCTIONSan Diego, Calif.Due by No date yetConstruction type: New primaryLand ownership: Interior Dept.Contractor: To be determined
Total miles: 4Miles built: 0Progress: 0%$72 million has been allocated to build this section of the wall at a cost of $18.0 million per mile.PRE-CONSTRUCTIONYuma, Tex.Due by No date yetConstruction type: New primaryLand ownership: Interior Dept.Contractor: To be determined
Total miles: 6Miles built: 0Progress: 0%$70 million has been allocated to build this section of the wall at a cost of $11.7 million per mile.PRE-CONSTRUCTIONEl Paso, Tex.Due by No date yetConstruction type: New primaryLand ownership: FederalContractor: To be determined
Total miles: 8Miles built: 0Progress: 0%$170 million has been allocated to build this section of the wall at a cost of $21.3 million per mile.PRE-CONSTRUCTIONSan Diego, Calif.Due by No date yetConstruction type: New secondaryLand ownership: PrivateContractor: To be determined
Total miles: 11Miles built: 0Progress: 0%$62 million has been allocated to build this section of the wall at a cost of $5.6 million per mile.PRE-CONSTRUCTIONEl Centro, Calif.Due by No date yetConstruction type: New secondaryLand ownership: DHSContractor: To be determined
Total miles: 5Miles built: 0Progress: 0%$25 million has been allocated to build this section of the wall at a cost of $5.0 million per mile.PRE-CONSTRUCTIONLaredo, Tex.Due by No date yetConstruction type: New primaryLand ownership: PrivateContractor: To be determined
Total miles: 52Miles built: 0Progress: 0%$1.3 billion has been allocated to build this section of the wall at a cost of $24.5 million per mile.PRE-CONSTRUCTIONEl Centro, Calif.Due by No date yetConstruction type: New secondaryLand ownership: PrivateContractor: To be determined
Total miles: 9Miles built: 0Progress: 0%$294 million has been allocated to build this section of the wall at a cost of $32.7 million per mile.Nick Miroff
Nick Miroff covers immigration enforcement and the Department of Homeland Security for The Washington Post. He was a Post foreign correspondent in Latin America from 2010 to 2017, and has been a staff writer since 2006.
Adrian Blanco
Adrián Blanco Ramos is a graphic reporter in the graphics department at The Washington Post. He previously worked at Spanish newspaper El Confidencial focusing on data visualization, data analysis and investigative journalism. He participated in the International Consortium of Investigative Journalist’s Paradise Papers investigation.
Josh Dawsey, Danielle Rindler and Chris Alcantara contributed to this report.
About this story
Data from The Washington Post reporting and U.S. government documentation about the border barriers obtained by The Washington Post.