The ‘trick’ was though, that I had added two custom fields to trac: estimated time and actual time (which is easily done by just adding a few trivial lines to trac.ini). As we created each ticket we collectively agreed on an estimated time. After having entered all tickets we were then in the happy position (using a custom sql-based query) to arrive at a precise total of estimated man hours — and based on that, of course, an estimate of cost and finish date.